MIL-PRF-55365H
4.4.4.1.1 Exponential. Exponential FR qualification shall be in accordance with the general and detailed
requirements in MIL-STD-690 and the following details:
a. Procedure I: Qualification at the initial FRL. Level "M" (1.0 percent) of FRSP-60 shall apply. Sample units
shall be subjected to the qualification inspection specified in group VI, table VI (see 4.4.2). The entire life
test sample shall be continued on test to 10,000 hours, as specified in 4.7.19.1, on completion of the 2,000
hour qualification tests.
b. Procedure II: Extension of qualification to lower FRL's. To extend qualification to the "P" FRL, data from
two or more voltages within a style may be combined. For FRL's "R" and "S", the following styles of similar
construction (see 4.6.1.1) may be combined: CWR09, CWR11, CWR19 and CWR29.
c. Procedure III: Maintenance of FRL qualification. Maintenance period B of FRSP-10 shall apply.
Regardless of the number of production lots produced during this period, the specified number of unit hours
shall be accumulated to maintain qualification.
4.4.4.1.2 Weibull. Weibull FR qualification will be granted only to manufacturers who have achieved FRL P for any
capacitor style covered by this specification in accordance with 4.4.4.1.1. To extend qualification to include Weibull
FRL's, the manufacturer shall demonstrate the capability of Weibull FR grading (see 4.7.20) to the qualifying activity.
If during two consecutive reporting periods there has been no production of the lowest Weibull FRL for which the
manufacturer is qualified, the manufacturer may be required, at the discretion of the qualifying activity, to submit a
product of each style to testing in accordance with the qualification inspection requirements. Failure to meet this
requirement shall result in a loss of the manufacturer's FR to the lowest FR last demonstrated.
4.4.4.2 Quality level verification. The contractor is responsible for establishing a quality system to verify the ppm
defect level of lots that are subjected to the group A inspections. The ppm defect level shall be maintained for each
specification sheet. The ppm defect level shall be based on a 6-month moving average.
4.5 Verification of qualification. Every 6 months, the manufacturer shall provide verification of qualification to the
qualifying activity. Continued qualification is based on meeting the following requirements.
a. MIL-STD-790 program.
b. The capacitor design has not been modified.
c. Lot rejection for group A does not exceed 5 percent or one lot, whichever is greater; not applicable to
d. Periodic group C inspection.
e. Verification of FRL's.
f.
PPM assessment. The ppm level defect shall be maintained for each performance specification sheet.
g. Continued qualification to non-ER (A level) shall be based upon continued maintenance of qualification for
the ER part FRL B.
In the event that there is no production of a single style ER or non-ER device during a maintenance period and the
manufacturer is listed for more than one style on the QPL, a report shall be submitted certifying that the manufacturer
still has the capabilities and facilities necessary to produce that product.
14
For Parts Inquires submit RFQ to Parts Hangar, Inc.
© Copyright 2015 Integrated Publishing, Inc.
A Service Disabled Veteran Owned Small Business