4.5 Verification of qualification. Every 6 months, the manufacturer shall provide verification of qualification to the
qualifying activity. Continuation of qualification shall be based on meeting the following requirements:
a. MIL-STD-790 program.
b. The capacitor design has not been modified.
c. Lot rejection for group A inspection does not exceed 10 percent or one lot, whichever is greater.
d. Periodic group B inspection.
4.6 Conformance inspection.
4.6.1 Inspection of product for delivery. Inspection of product for delivery shall consist of group A inspection.
4.6.1.1 Inspection and production lot.
4.6.1.1.1 Inspection lot. An inspection lot shall consist of all capacitors of the same voltage-temperature
characteristics, produced under essentially the same conditions and offered for inspection during a single work
month. Each inspection lot shall be kept separate from every other inspection lot. The capacitance values and
voltages produced shall be represented in the lot in approximately the ratio of production.
4.6.1.1.2 Production lot. A production lot shall consist of all capacitors of the same voltage rating, nominal
capacitance value, voltage-temperature characteristic, and termination finish. The manufacture of all parts in the
production lot shall have been started, processed, assembled, and tested as a group. Lot identity shall be maintained
throughout the manufacturing cycle.
4.6.2 Group A inspection. Group A inspection shall consist of the inspections specified in table VI in the order
shown.
4.6.2.1 Subgroup 1.
4.6.2.1.1 Sampling plan. Subgroup 1 shall be performed on a production lot basis on 100 percent of the product
supplied under this specification. Capacitors failing the tests of this subgroup shall be removed from the lot. If, during
the 100 percent inspection, screening requires that more than 8 percent of the capacitors be discarded (8 percent
defective allowable (PDA)), the entire lot shall be rejected.
4.6.2.1.2 Manufacturer's production inspection. If the manufacturer performs tests similar to those specified in
subgroup 1, table VI as the final step of their production process, group A, subgroup 1 inspection may be waived and
the data resulting from the manufacturer's production tests may be used instead. Authority to waive the subgroup 1
inspections shall be granted by the qualifying activity only. The following criteria must be complied with:
a. Tests conducted by the manufacturer during production shall be clearly identical to, or more stringent than,
that specified for subgroup 1.
b. Manufacturer subjects 100 percent of the product supplied under this specification to their production tests.
c. The parameters measured and the failure criteria shall be the same as, or more stringent than, those
specified herein.
d. The lot rejection criteria is the same as, or more stringent than, that specified herein.
e. The manufacturer shall make available all information concerning the test procedures and instrumentation
used in their production tests.
f. Once approved, the manufacturer shall not change the test procedures or criteria without prior notification of,