MIL-PRF-39001E
4.4.1 Sample size. The number of sample units comprising a sample of capacitors to be submitted for
qualification inspection shall be as specified in table VIII, or in appendix A of this specification. The sample shall be
taken from a production run and shall be produced with equipment and procedures normally used in production.
Each capacitor style shall be qualified separately.
4.4.2 Inspection routine. Sample units shall be subjected to the qualification inspection specified in table VIII, in
the order shown. All sample units shall be subjected to group I and group II tests. These sample units shall then be
divided as shown in table VIII for group III to group VI, inclusive, and subjected to the tests for their particular group.
The units subjected to life test at rated conditions shall be continued on test for 48,000 additional hours.
4.4.3 Failures. Failures in excess of those allowed in table VIII shall be cause for refusal to grant qualification
approval.
4.4.4 FRL and quality level verification.
4.4.4.1 Failure rate (FR) qualification and lot conformance FR inspection. FR qualification and lot conformance
FR inspection shall be in accordance with the general and detailed requirements of MIL-STD-690 and the following
details:
a. Procedure I: Qualification at the initial FRL. Level M (1.0 percent), of FRSP-90 shall apply. Upon successful
completion of the 2,000-hour qualification test (group V, table VIII), those sample units which have been
subjected to rated conditions shall be continued on test for an additional period as specified in 4.7.16.3.
b. Procedure II: Extension of qualification to lower FRL. To extend qualification to the P (0.1 percent), R (0.01
percent), and S (0.001 percent) FRLs, data from two or more voltages within a style and of similar
construction may be combined. For FRLs R and S, two or more styles of similar construction (see 4.6.1.1.1)
may be combined.
c. Procedure III: Maintenance of FRL qualification. Maintenance period B of FRSP-10 shall apply. Regardless
of the number of production lots produced during this period, the specified number of unit hours shall be
accumulated to maintain qualification (see 4.5f).
4.4.4.2 Quality level verification. The manufacturer is responsible for establishing a quality system to verify the
ppm defect level of lots that are subjected to the group A inspections. The ppm defect level can be maintained for
each specification sheet, or alternatively can combine all specification sheets. The ppm defect level shall be based
on a 6-month moving average.
4.5 Verification of qualification. Every 6 months the manufacturer shall provide verification of qualification to the
qualifying activity. Continued qualification is based on meeting the following requirements:
MIL-STD-790 program.
a.
b. The capacitor design has not been modified.
c. Lot rejection for group A does not exceed 10 percent or one lot, whichever is greater.
d. Periodic group C inspection.
e. Verification of FRLs.
f. PPM assessment.
g. Continued qualification to non-ER (level C) shall be based upon maintenance of qualification for the ER part