MIL-C-11272E
4.4.4 Verification of qualification. Every 6 months, the manufacturer shall verify the retention of qualification to the
qualifying activity. In addition, the manufacturer shall immediately notify the qualifying activity whenever group B
inspection results indicate failure of the qualified product to meet the requirements of the specification.
Verification of qualification shall be based on meeting the following requirement
a.
The capacitor has not been modified.
b.
Lot rejection for group A inspection does not exceed the group A sampling plan.
c.
Periodic group B inspection requirements have been met.
4.5 Conformance inspection.
4.5.1 Inspection of product for delivery. Inspection of product for delivery shall consist of group A inspection.
4.5.1.1 Inspection lot. An inspection lot shall consist of all capacitors of the same style produced under
essentially the same conditions, and offered for inspection at one time.
4.5.1.2 Group A inspection. Group A inspection shall consist of the examinations and tests specified in table V, in
the order shown.
4.5.1.2.1 Sampling plan. The sampling plan shall be as specified in table V In the event of one or more failures,
the lot shall be rejected.
4.5.1.2.2 Rejected lots. If an inspection lot is rejected, the supplier may rework it to correct the defects, or screen
out the defective units, and resubmit for reinspection. A new sample of parts shall be randomly selected in
accordance with table V. Such lots shall be kept separate from new lots, and shall be clearly identified as
reinspected lots. If one or more defects are found in this second sample, the lot shall be rejected and shall not be
supplied to this specification.
TABLE V. Group A inspection.
Sampling procedure
Test method
Examination or test
Requirement
paragraph
paragraph
Visual and mechanical examination:
See table VI
Material
3.3 to 3.3.2, incl
Physical dimensions
Design and construction (other than
physical dimensions)
Marking 1/
Workmanship
3.20 to 3.20.2, incl
Dielectric withstanding voltage
See table VI
Insulation resistance
Capacitance
Dissipation factor
Barometric pressure
Life (performance check)
1/ Marking defects are based on visual examination only. Any subsequent electrical defects shall not be used as
a basis for determining marking defects.